Honeywell AS907 (HTF7000) Engine Inspection Intervals

August 2025

At Duncan Aviation, we understand the importance of predictability in engine maintenance planning. Most inspection tasks on the Honeywell AS907 (HTF7000) are straightforward, offering consistent turn times and cost expectations.

However, it's important to note that the Borescope inspections of turbine and compressor components can reveal issues that may extend downtime and increase costs, especially in engines that have not incorporated SB (Service Bulletin) 72-9082 and AS907-72-9076.

Engines without this SB are significantly more likely to require in-depth disassembly due to discrepancies. Planning ahead for this potential can help keep your operations running smoothly.

These are the specific inspections that require the additional attention and planning.

Challenger 300: AS907-1-1A (HTF7000) Engine Challenger 350/3500: AS907-2-1A (HTF7350) Engine

  • 72-40-00-280-801 Special Detailed Inspection of the engine combustor module
  • 72-50-00-280-801 Special Detailed Inspection of the engine HPT module
  • 72-50-00-280-804 Special Detailed Inspection of the engine LPT module

These tasks are the Borescope requirements of the hot section.  Most commonly due at 4800 hours*

  • 72-30-00-280-801 Special Detailed Inspection of the Compressor Module. Most commonly due at 9,600 hours*

*Engines that are not in compliance with AS907-72-9001 R2, AS907-72-9044 R4, AS907-72-9048 R0, AS907-73-9004 R1, and AS907-76-9021 R1 will be on the 4000-hour Hot Section Borescope and 8,000-hour Compressor Borescope intervals.

Gulfstream G280: AS907-2-1G (HTF7250) Engine

  • 724101 Engine Combustor Module – Special Detailed Inspection
  • 725003 Engine HP Turbine Module (Borescope) – Special Detailed Inspection
  • 725001 Engine LP Turbine Module – Special Detailed Inspection

These tasks are the Borescope requirements of the hot section.  Most commonly due at 4800 hours*

  • 723014 Engine Compressor Section – Special Detailed Inspection. Most commonly due at 9,600 hours*

*Engines that are not in compliance with AS907-72-9001 R2 and AS907-76-9021 R1will be on the 4000-hour Hot Section Borescope and 8,000-hour Compressor Borescope intervals

Embraer Legacy 450/500 and Praetor 500/600: AS907-3-1-E (HTF7500) Engine

  • 72-40-00-001 SDI Special Detailed Inspection (Borescope) of Combustor Module
  • 72-51-00-001 SDI Special Detailed Inspection (Borescope) of High Pressure (HP) Turbine Module
  • 72-55-00-001 SDI - Special Detailed Inspection (Borescope) of Low Pressure (LP) Turbine Module

These tasks are the Borescope requirements of the hot section.  Most commonly due at 4500 hours*

  • 72-30-00-002 SDI - Special Detailed Inspection (Borescope) of Compressor Section. Most commonly due at 9,000 hours*

*Engines that are not in compliance with AS907-72-9001 R2 and AS907-76-9021 R1 will be on the 4000-hour Hot Section Borescope (tasks 72-40-00-003, 72-51-00-009, 72-55-00-013) and 8,000-hour Compressor Borescope intervals (Task 72-30-00-011).

Cessna 700 Longitude: AS907-2-1S (HTF7700L) Engine

  • 72-40-00-201 Engine LMM 72-05-25 Chapter 05-20-00 Table 8008 Special detailed inspection of the engine combustor module
  • 72-51-00-201,75-21-00-202 Engine LMM 72-05-25 Chapter 05-20-00 Table 8008 detailed inspection of the engine HPT module
  • 72-55-00-201 Engine LMM 72-05-25 Chapter 05-20-00 Table 8008 Special detailed inspection of the engine LPT module

These tasks are the Borescope requirements of the hot section.  Most commonly due at 4800 hours*

  • 72-30-00-202 Engine LMM 72-05-25 chapter 05-20-00 Table 8010 Special detailed inspection of the engine compressor module. Most commonly due at 9,600 hours*

*Engines that are not in compliance with AS907-72-9001 R2, AS907-76-9021 R1 will be on the 4000-hour Hot Section Borescope and 8,000-hour Compressor Borescope intervals.

A note for all AS907 (HF7000)

Engines that are still on the shorter intervals. The SB requirements to extend the longer intervals can be performed on wing in a couple of days. AS907-72-9001 Compliance is best addressed during Start Fuel Nozzle Replacement. The exception to this is the AS907-1-1A (HTF7000), which is pre-SB AS907-72-9044. This is a significant amount of work. There are very few pre-SB AS907-72-9044 engines remaining.

Duncan Aviation Contact

For technical support for the Honeywell AS907 (HTF7000) engine, contact Shawn Schmitz, Engine Tech Rep Program Manager at +1 402.479.8166, or via email at Shawn.Schmitz@DuncanAviation.com. 